The department makes a payment against a BCO business contract or consultant agreement by creating a BFS requisition including the steps below:
· In BFS, go to Purchasing> Requisitions> Add/Update Requisitions.
· Click “Add” to “Add a New Value.”
· Complete the information as you would on any requisition.
· On the right side of the page, click “Add Comments.”
· Click “Copy Standard Comments.”
· Select Comment Type “BUS” and Comment ID “1” and fill in the “Contract/ Project Name.”
· Upload a copy of the signed contract as an attachment.
· In “Requisition Defaults” select “Special Handling” as the Buyer.
· After requisition approval, you should receive a PO number within the same day.
Do not send the purchase order to the vendor. (Printable instructions)
To increase the dollar amount of a purchase order:
First an amendment to the agreement (issued through BCO) needs to be fully signed, and then the department creates a change order to the BFS departmental purchase order. Do not send the change order to the vendor.